Supervision System

Current Construction Supervision System.

Public Area

  • Construction techonlogy management act

    • Target
      construction work execuled by the order(22 disciplines of construction worthy of over 10 billion won)
    • Nature
      agent service of construction supervision(responsible supervision)
    • Executed by
      professional supervision company(total, civil engineering, construction, equipment)
  • Engineering Technology Promotion Act

    • Target
      construction personnel except work manager of supervisor in charge
    • Nature
      construction supervision
    • Executed by
      actors of engineering of relevant areas
    • Main department
      ministry of science and technology

Private Area

  • Gerneral Building(Civil Engineering Area)

    • Target
      constrruction or repair subject to construction approval
    • Nature
      execultion supervision
    • Executed by
      architecture office

    But, public bilding is subject to responsible supervision in accordance with Act on Construction Technology Managemnet

  • Housing construction supply side(Town House)

    • Target
      construction work of over 20 private houses
    • Nature
      work supervision
    • Executed by
      below 300 households -> architect office over 300 households -> professional supervision company

Supervision Work

Step-By-Step Supervision Work

Step-By-Step Supervision Work

  • Commencement Stage

    • Understand requirements of orderer and agreemnets, review and reflect site confitions

    • Review process plan of overall work(master, milestone schedule)

    • Review, reflect workability, analyze VE, LCC of design drawing

    • Review materials and support purchase procuremnet

    • Changr design and establish technical administration process of other tasks

    • Instruct system construction and establish various kinds of construction works

    • Plan integrated management

  • Execution Stage

    • Qiality management plan

    • Safety and enviroment management plan

    • Process management plan

    • Imtergrated management

  • Stage Of Commissioning And Completion

    • Establish schedule plan related to commissioning/completion of work for each device and main system for each facility

    • Establish preliminary comoletion inspection plan

    • Prepare inspection table, manage inspection, commissioning and complementary execution plan teansfer of facility according to completion of work and establish procedure

    • Settle construction cost for the completed parts as well as according to completion prepare and submit dinal report